Q. If I install Client Access Server (CAS) on an Exchange 2010 Mailbox Server that's a member of a Database Availability Group (DAG), can I still use software to load balance the CAS?

John Savill

November 26, 2009

1 Min Read
ITPro Today logo

A. No, you can't have failover clustering and network load balancing on the same server. Even though using DAGs doesn't require you to configure failover clustering, the failover clustering feature is still being used under the hood, so you can't also use network load balancing. To provide load balancing between multiple CAS servers that are installed on DAG mailbox servers, you need to use a hardware load balancer or a solution such as ISA Server.

Related Reading:



Check out hundreds more useful Q&As like this in John Savill's FAQ for Windows. Also, watch instructional videos made by John at ITTV.net.

About the Author(s)

Sign up for the ITPro Today newsletter
Stay on top of the IT universe with commentary, news analysis, how-to's, and tips delivered to your inbox daily.

You May Also Like